- 1952 erection of HUTA WARSZAWA [Warsaw Steel Plant] begins
- 1957 start-up of a Steel Foundry, the first production department of Huta Warszawa
- 1958 Steel Shop and Forging Shop begin to operate
- 1960 a Blooming Mill begins to operate
- 1961 start-up of a Drawing Mill
- 1962 start-up of a Heavy Section and a Small Section Rolling Mills.
- 1965 start-up of a Cold Strip Mill
- 1968 start-up of a Medium Section Rolling Mill
- 1992 Huta Warszawa is privatized on the basis of a joint-venture agreement with LUCCHINI Group, establishing HUTA L.W. Sp. z o.o..
- 1998 start-up of a new Steel Shop (EAF 80t, LF 80 t and a four-strand CC)
- 2001 modernization of the Steel Shop continues. Start-up of a VD 80t
- 2004 the Cold Strip Mill is shut down
- 2005 Arcelor Group takes over Huta L.W. The Company's name is changed to Arcelor Huta Warszawa Sp. z o.o.. The Forging Shop is shut down. Erection of a new Hot Rolling Mill begins.
- 2006 Arcelor and Mittal groups merge. The Small Section Rolling Mill is shut down.
- 2007 50th anniversary of Huta Warszawa
|